For the first time, wind turbines are now running on a sea dike. In Eemshaven, within the Dutch province of Groningen, RWE has erected three wind power plants with an installed capacity of 7.5 megawatts, which became fully operational in September 2022.

In order to safely install the individual components in this particular location, with limited space around it, RWE relied on some innovative installation methods. 

installation of the turbine components

For the installation of the upper turbine components, for example, a special climbing crane was used, which climbed upwards by inserting individual segments as construction progressed. In addition, the turbines were erected on so-called cutter soil mixing (CSM) panels. 

In this process, the existing soil is strengthened by mixing it with concrete and covered with a layer of sand on which the foundations are then built. In this way, the wind turbines are not directly connected to the subsoil and can safely move with it if the dike settles.

wind turbines Running on a sea dike

This world first and all the installation challenges are paying off"

Katja Wünschel, CEO Onshore Wind and Solar Europe & Australia at RWE Renewables, said: "This world first and all the installation challenges are paying off. The wind conditions in this exposed location are excellent. The three turbines will generate sufficient green power to supply up to 7000 Dutch households annually."

He adds, "And we have gained valuable insights from completing this project, which will enable us to erect wind farms on dikes in other locations too. My particular thanks go to the Noorderzijlvest Water Board and the consent authorities involved for their many years of constructive cooperation.”

Potential environmental impacts

Over the past few years, RWE and the owner of the dike, the Noorderzijlvest Water Board, meticulously analyzed the installation process, with a view to dyke safety and the potential environmental impacts of the project, and incorporated this into a technically complex design. The most important aspect of the project development process was the protection of the dyke to ensure its flood-water prevention function was not impaired in any way.

The electricity from the wind farm has already been marketed: In February 2022, RWE signed a power purchase agreement with ASML, the world’s largest provider of lithographic systems for the semiconductor industry, on the supply of green power, which will be generated at this wind farm in Oostpolderdijk among other places.

Download PDF version Download PDF version

In case you missed it

Siemens Boosts Additive Manufacturing With Xcelerator
Siemens Boosts Additive Manufacturing With Xcelerator

Under the motto ‘Let’s advance Manufacturing,’ Siemens and selected partners will demonstrate at Formnext 2024 how additive manufacturing (AM) is becoming an inno...

Stay Scam-Aware: Tips From Ameren For Holiday Season
Stay Scam-Aware: Tips From Ameren For Holiday Season

Ahead of Utility Scam Awareness Day on Nov. 20, Ameren is reminding residential and business customers not to let their guard down during the busy holiday season. Customers should...

Eaton & Treehouse Partner For Smart Home Electrification
Eaton & Treehouse Partner For Smart Home Electrification

Intelligent power management company - Eaton announces a collaboration with Treehouse to enable high-quality, cost-effective and code-compliant residential electrification projects...

vfd