With the start of the last construction phase, the offshore wind project Arkona enters the home stretch. After only ten months of construction, the first of 60 wind turbines was successfully installed off the coast of Rügen in the German Baltic Sea. E.ON and Equinor's joint project is still ahead of schedule.

Sea Challenger 

The turbines consist of a 100-meter-long tower, three rotor blades, and the turbine house. With a total weight of almost 1,000 tons, a turbine weighs as much as 200 elephants. The tip of the rotor blades reaches a height of 180 meters above sea level and towers 30 meters above Cologne Cathedral.

All turbine components will be stored and prepared in the Arkona base port of Mukran in Sassnitz, loaded onto the installation ship ‘Sea Challenger’, and finally installed on the previously laid foundations consisting of monopiles and so-called transition pieces.

turbines for power generation

At the same time, the substation is being commissioned and the connection to the mainland is being completed

Directly after the installation of the components, the project team prepares the turbines for power generation. At the same time, the substation is being commissioned and the connection to the mainland is being completed.

The entire team has done a great job in recent months to start the turbine installation ahead of schedule. We are confident that we will soon be producing clean and sustainable electricity with the first turbines,” says Holger Matthiesen, Project Director Arkona. The complete commissioning of the entire wind farm is scheduled for the beginning of 2019 at the latest.

renewable energy

The Arkona project is located 35 kilometers northeast of the island of Rügen. The wind farm will have an output of 385 megawatts (MW) and is expected to supply around 400,000 households with renewable energy in 2019. The investment volume amounts to €1.2 billion.

Compared to conventionally generated electricity, Arkona saves up to 1.2 million tons of CO2 per year. 60 turbines in the six-megawatt class from Siemens will be installed. Arkona is a joint venture between E.ON and the Norwegian energy company Equinor.

Download PDF version Download PDF version

In case you missed it

Emtelle USA Enhances Testing Capabilities With New Test Track
Emtelle USA Enhances Testing Capabilities With New Test Track

Emtelle USA, the American division of the globally renowned Emtelle Group, proudly announces the addition of an advanced test track at its fully operational 300,000 sq. ft facility...

PNR RailWorks Wins Five-Year Contract With VIA Rail Canada
PNR RailWorks Wins Five-Year Contract With VIA Rail Canada

PNR RailWorks Inc., Canada’s largest and most experienced full-service railroad contractor, has won a five-year contract with VIA Rail Canada Inc. (VIA) to perform maintena...

Leep Utilities Launches EHV Team For Data Centers
Leep Utilities Launches EHV Team For Data Centers

Following several high-profile data center contract wins, Leep Utilities - one of the UK's pioneering owners and operators of last-mile utility networks - has launched a specialist...

vfd