On December 9, 2020, the world’s first 220 kV Distributed Power Flow Controller (DPFC)supplied by NR Electric, Huzhou DPFC pilot project of State Grid Zhejiang Electric Power Co., Ltd., has successfully completed all system tests in the first phase and has been put into operation.

DPFC is an advance type of flexible power flow control device based on high-power power electronic technology. It can dynamically optimize the line impedance characteristics, effectively control the power flow transfer, and enhance the load capacity & security of regional power grid.

Huzhou DPFC pilot project

Construction of Huzhou DPFC project can effectively solve the problem of overload line in Huzhou Power Grid

The total design capacity of Huzhou DPFC pilot project is 58MVA. It is estimated that the dynamic transfer of power flow can reach 150MW. The first phase project has the capacity of power flow transfer of 64MW.

The construction of Huzhou DPFC project can effectively solve the problem of overload line in Huzhou Power Grid, optimize the power flow distribution of local power grid, enhance the regional power supply capacity, and improve the overall efficiency of the power grid, which has great social and economic benefits.

Huzhou DPFC adopts outdoor arrangement scheme

Huzhou DPFC adopted the outdoor arrangement scheme of converter valve, which is the first time of this kind of application for 220 kV transmission lines in the world.

NR Electric has provided a complete set of converter valve equipment, protection & control system, as well as relevant supporting facilities for Huzhou DPFC pilot project.

flexible AC / DC transmission technology

In recent years, NR Electric has been committed to the development of flexible AC / DC transmission technology.

Among them, the complete set of power flow controller series developed by NR Electric have been successfully applied to 220kV Nanjing UPFC project and 500kV Sunan UPFC project, which has played an important role in improving the utilization efficiency of power grid and ensuring the safe operation of power grid.

Flexible engineering scheme

The 220kV Huzhou DPFC pilot project put into operation has realized a more flexible engineering scheme for special application scenarios on the basis of the original unified power flow controller, which further reflects the leading level of NR in the field of flexible AC / DC transmission technology.

Download PDF version Download PDF version

In case you missed it

Siemens Boosts Additive Manufacturing With Xcelerator
Siemens Boosts Additive Manufacturing With Xcelerator

Under the motto ‘Let’s advance Manufacturing,’ Siemens and selected partners will demonstrate at Formnext 2024 how additive manufacturing (AM) is becoming an inno...

Stay Scam-Aware: Tips From Ameren For Holiday Season
Stay Scam-Aware: Tips From Ameren For Holiday Season

Ahead of Utility Scam Awareness Day on Nov. 20, Ameren is reminding residential and business customers not to let their guard down during the busy holiday season. Customers should...

Eaton & Treehouse Partner For Smart Home Electrification
Eaton & Treehouse Partner For Smart Home Electrification

Intelligent power management company - Eaton announces a collaboration with Treehouse to enable high-quality, cost-effective and code-compliant residential electrification projects...

vfd