Download PDF version

The No.5 1000MW supercritical generating unit at the State Grid Hanchuan Power Plant was recently operated under full load and connected to the grid.

It marks the completion of the first 1000MW unit overhauling project undertaken by Shanghai Electric. Generators and gas turbines of the project are from Shanghai Electric.

No.5 unit overhauling project involves more tasks

Compared with the Class B maintenance project for No.6 unit in 2019, the No.5 unit overhauling project involves more tasks and uncertainties. Since the commencement in early April, the Hanchuan Project Department has overcome various difficulties as Hubei has set strict measures for COVID-19 prevention and control.

Emergency spare parts have been quickly provided to ensure timely supply and on-schedule task completion. Excellent work in turbine buckling, motor startup, and grid connection is highly recognized by the owner.

Download PDF version Download PDF version

In case you missed it

NR Powers Guangdong With Reliable Converter Valves
NR Powers Guangdong With Reliable Converter Valves

On January 20, 2022, the first converter valve of the China Great Bay Area DC back-to-back project was successfully put into operation for the first time, marking an important step...

NR Luxi Island Microgrid Success In Black Start
NR Luxi Island Microgrid Success In Black Start

Luxi Island microgrid system, which was designed, supplied, commissioned and delivered by NR, has been successfully put into operation. The system effectively solved the black sta...

Lanner Unveils IEC 61850-3 Certified Industrial Computer ICS-P770 Powered by Intel® Xeon® 6 Processor
Lanner Unveils IEC 61850-3 Certified Industrial Computer ICS-P770 Powered by Intel® Xeon® 6 Processor

Lanner Electronics, a global pioneer in industrial computing and network security solutions, proudly announces the launch of the ICS-P770. An IEC 61850-3, IEEE 1613, and EN50121-4...

vfd