The Federal Emergency Management Agency (FEMA) approved nearly $600 million for the purchase of materials and equipment needed to rebuild Puerto Rico's power grid. The federal share will allow for the advance purchase of materials so that resources will be available once the reconstruction work begins.

Federal Disaster Recovery Coordinator, José G. Baquero, explained that the Puerto Rico Electric Power Authority (PREPA) has already submitted to the agency an initial list of materials and equipment that are currently in short supply, that usually have a long lead time or that could be impacted by the future events.

transmission and distribution materials

This is an extensive requirement which includes the areas of transmission and distribution, substations, and telecommunications. The goal is to have the materials in time for the work to begin. We are very excited to see how the work is beginning to take shape,” said the official.

Among the materials included in this project are about 2,500 circuit miles of transmission lines, roughly 23 miles of submarine cable for the municipalities of Vieques and Culebra, over 300 substations, nearly 200,000 transformers, and nearly 13,400 miles of feeders, among other necessary equipment.

reconstruction of the electrical grid

This obligation is the result of the active and proactive work we have executed together with PREPA, FEMA"

Manuel A. Laboy Rivera, Executive Director of the Central Office for Recovery, Reconstruction and Resiliency (COR3), said, "This obligation is the result of the active and proactive work we have executed together with PREPA, FEMA, and the close collaboration with LUMA.”

I reiterate that the reconstruction of the electrical grid has already begun and the purchase of the equipment under this significant obligation will allow for the streamlined development of other projects."

Money disbursed

Rivera adds, “Currently, we have disbursed $1.6 billion in emergency categories and $7.1 million for permanent works.”

As the projects move forward in their development, and PREPA or LUMA submit their requests for reimbursement, we will promptly address them so that the money disbursed will continue to further the reconstruction of other infrastructure in the electric system.”

restore the power grid

These funds are in addition to 18 other projects to restore the power grid for a total of over $700 million. The electric system reconstruction also has an additional $9.6 million for mitigation measures, such as replacing poles with ones that can withstand winds of up to 160 miles per hour, emergency generators to prevent damage to replacement batteries at substations and the elevation of substations located in flood zones.

FEMA has approved over $12.8 billion to PREPA for permanent and emergency work to address damages from Hurricane Maria and the 2020 Earthquakes. Of this total, $9.4 billion was awarded through FEMA's Accelerated Awards Strategy (FAAST).

Download PDF version Download PDF version
  • Related companies
  • FEMA
  • View all news from
  • FEMA

In case you missed it

Explore Innodisk's DDR5 6400 For AI And Telehealth
Explore Innodisk's DDR5 6400 For AI And Telehealth

Innodisk, a global AI solution provider, announces its DDR5 6400 DRAM series, featuring the industry’s largest 64GB single-module capacity. This 6400 series is purpose-b...

Leaf Disposal Tips From Ameren Missouri
Leaf Disposal Tips From Ameren Missouri

The leaves are falling, and it may seem easy to rake them right into the water – but that can create a number of issues for aquatic life, as well as humans and pets living al...

Ameren Illinois Team Excels At International Lineman's Rodeo
Ameren Illinois Team Excels At International Lineman's Rodeo

Ameren Illinois customers served by the Marion Operating Center (OC) know that journeymen linemen - Jason Novak, Clayton Gulley and Austin Lewis are great at keeping the lights on...

vfd